Gap Filler Detail

1962 – National Archives of Canada


APPENDIX "A" to
S949-105 TD2240 (CCE)
dated 14 Sep 62

Sites: Algonquin Park, Belleterre, Elliot Lake, Formosa Relocated, Lac Ste Marie, Nicolet, Scotch Settlement Relocated, St Joseph, Timmins, Tobermory

Progress of Construction - 95%

Description of Construction Completed:

  1. Access Road - 90%

  2. Building Site - 90%

  3. Tower Foundations - 100%

  4. Radar Building - 95%

  5. Power & Accommodation Building - 95%

  6. Fuel Oil Storage Facilities - 95%

  7. Security Fencing - 100%

  8. Electrical Grounding System - 95%

Description of Work to be Completed:

  1. Access Road - final gravelling and shaping, repair of damage to surface, ditches and culverts

  2. Building Site - final grading and clean-up

  3. Radar Building - final electrical and mechanical work

  4. Power & Accommodation Building - installation of diesel alternator set and associated equipment, final electrical, mechanical and plumbing work.

  5. Fuel Oil Storage Facilities - final piping

  6. Electrical Grounding System - final testing

  7. Commercial Power Line and Transformers

Time Required to Complete Construction: three (3) months from approved DND-8 to DCL.

Status of Contracts: Terminated at above stage of completion.