Progress of Construction - 95%
Description of Construction Completed:
- Access Road - 90%
- Building Site - 90%
- Tower Foundations - 100%
- Radar Building - 95%
- Power & Accommodation Building - 95%
- Fuel Oil Storage Facilities - 95%
- Security Fencing - 100%
- Electrical Grounding System - 95%
Description of Work to be Completed:
- Access Road - final gravelling and shaping, repair of damage to surface, ditches and culverts
- Building Site - final grading and clean-up
- Radar Building - final electrical and mechanical work
- Power & Accommodation Building - installation of diesel alternator set and associated equipment, final electrical, mechanical and plumbing work.
- Fuel Oil Storage Facilities - final piping
- Electrical Grounding System - final testing
- Commercial Power Line and Transformers
Time Required to Complete Construction: three (3) months from approved DND-8 to DCL.
Status of Contracts: Terminated at above stage of completion.