10-36-80/5 Vol 3 (DCEP)
MEMORANDUM
29 Nov 63
Ref: 10-36-80/5 (DCEP) 15 Nov 63
10-36-80/5 (Eng-4) 20 Nov 63
D Arch C
Completion of Plans & Specifications
Gap Filler Radar Stations, Various
Based on tentative target dates for the completion of the road work on the various projects within the Eng-4 Section, the following are suggested target dates for the completion of specifications and estimates:
| Week Ending | Station |
|---|---|
| Dec 13/63 | Sparta |
| Dec 20/63 | Beaver Tower |
| Jan 10/64 | Graham |
| Jan 17/64 | Taschereau |
| Jan 24/64 | Nishkotea Lake |
| Jan 31/64 | La tuque |
| Feb 7/64 | St Hedwidge |
| Feb 14/64 | Hastings & Atikokan |
| Feb 21/64 | Gowganda |
| Feb 28/64 | Stoney Creek & Biscotasing |
| Mar 6/64 | L'Ascension |
| Mar 13/64 | Nobel |
| Mar 20/64 | Mattawa |
| Mar 27/64 | Chapleau & Westport |
Major jobs have been allocated one week each, minor jobs have been allocated one-half week each. There is on specific priority at this time as long as one major job or two minor jobs are finished each week. The possibility of a speed up must be kept in mind if approval is received to proceed to contract and this becomes a crash programme.
(MC Hyslop) W/C
DCEP
2-5777