File 122-7-193-09-1
| Contractor | Roy Const & Supply |
| Awarded | Feb 7/62 |
| Contract comp date | August 15/62 |
| Value of contract | $170,000.00 |
| Value of work completed July 31, 1962 | $130,000.00 |
| Current estimated completion date | August 31, 1962 |
| Access Road | Complete |
| Tower Fnds | Complete |
| Tower Erection | Not started |
| Acc Bldg | Fnds complete Floor slab poured Bldg erected Elect & Mech installations underway |
| Radar Bldg | Same status as Acc Bldg |
| Passageway | Fnds poured Framing complete Roofing and and siding not started |
| Building Site | Rough grading complete Fencing not started Brush control complete |
| Fuel Tanks | 2000 gal tank complete except for painting and piping 50,000 gal tank dyke complete Tank erection underway, to be completed August 10 |
| Diesel Generator | Not shipped - expected to arrive on site week of August 12 |
Recommendation re termination of contract:
All work should be completed except: