CHAPLEAU
File 122-7-193-O33-1
Contractor | Chisnell-Ganton |
Awarded | February 23, 1962 |
Contract comp date | July 31, 1962 |
Value of contract | $104,000.00 |
Value of work completed July 31, 1962 | $60,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Fnds complete Floor slab not in Steelox Bldg erected and line Electrical - not started Mechanical - not started Painting - not started |
Radar Bldg | Same status as Acc Bldg |
Passageway | Fnds complete Framing complete Roofing and siding not started |
Building Site | Rough grading complete Fencing not started - Material not on site Brush control - not done |
Fuel Tanks | 50,000 gal tank erected 2000 gal tank - funds complete tanks not on site |
Diesel Generator | Not delivered to site |
Recommendation re termination of contract:
Instructions should be issued for all work to stop at once except that:
Diesel generators and radar towers should not be delivered. Arrangements for storage to be made by DCL/RCAF.