Gap Filler Detail

1962 – National Archives of Canada


122-7-193-C33-1

Aug 9/62

Mr JD McIlveen,
Branch Manager,
Toronto, Ont

Gap Filler - Chapleau

Please refer to your status report dated July 31st.

The electrical, mechanical and painting in the accommodation building should not proceed. The passageway roofing and siding should be completed in order that there is closed and secure storage for items of equipment etc that are not installed. The fencing need not be completed. The diesel generators will not be shipped.

LD Briden,
Assistant Chief Engineer,
(Field Project)