TIMMINS
File 122-7-193-T8-1
Contractor | Temiskaming Const |
Awarded | December 15, 1961 |
Contract comp date | July 31, 1962 |
Value of contract | $88,000.00 |
Value of work completed July 31, 1962 | $75,000.00 |
Current estimated completion date | August 15, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Complete except for Mech & Elect - 30% Painting |
Radar Bldg | Same status as Acc Bldg |
Passageway | Complete |
Building Site | Rough grading complete Fence complete Brush control not done yet |
Fuel Tanks | 2000 gal tank installed but not hooked up or painted |
Diesel Generator | On site, now being installed |
Recommendation re termination of contract:
All work should be completed except for radar tower installation.