File No: 122-7-193-N16-1
DEFENCE CONSTRUCTION (1951) LIMITED
Rm 2M6 Winnipeg Gen PO Building,
266 Graham Avenue,
Winnipeg 1, Manitoba
August 3, 1962.
TA Jones Company Limited,
Phoenix Building
PORT ARTHUR, Ontario
Dear Sirs:
Re: Construction of Gap Filler Radar Station,
NIPIGON, Ontario
This letter will confirm the verbal advice of our Project Supervisor, Mr GW Slee, to the effect that we have been advised by the Department of National Defence to stop all work on the current Gap Filler Program, including the above noted project.
This work stoppage, of course, is to be carried out as economically as possible. We, therefore, with regret, instruct you to cease all construction operations on the referenced job, with the exception of the following cleanup tasks.
Work on Items A and B should be completed not later than two weeks from now.
It is requested that you provide this office in writing, as soon as possible, with a detailed breakdown of the cancellation charges that will result, due to the termination of the work.
We respectfully request your full cooperation in the closing out of this contract as quickly and as economically as possible.
Yours very truly,
AM Anderson, P Eng
Branch Manager
AMA/ss