WESTPORT
File 122-7-193-W11-1
Contractor | T A Andre & Sons |
Awarded | February 16, 1962 |
Contract comp date | June 30, 1962 |
Value of contract | $68,000.00 |
Value of work completed July 31, 1962 | $30,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Subgrade complete Gravelling now underway, will be complete by Aug 8 |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Fnd complete Conc floor complete Steelox shell erected |
Radar Bldg | Same status as Acc Bldg |
Passageway | Complete except for door and electrical |
Building Site | Rough graded only No fencing |
Fuel Tanks | 2000 gal tank in place - no piping |
Diesel Generator | Not delivered |
Recommendation re termination of contract:
Advise contractor to cease work at once. If Steelox is to be dismantled then site can be restored to original shape. If not, then fence should be installed.