ONTARIO BRANCH
GAP FILLER RADAR STATIONS

STATUS REPORT AS OF
JULY 31, 1962

National Archives of Canada


WESTPORT

File 122-7-193-W11-1

ContractorT A Andre & Sons
AwardedFebruary 16, 1962
Contract comp dateJune 30, 1962
Value of contract$68,000.00
Value of work completed July 31, 1962$30,000.00
Current estimated completion dateSeptember 30, 1962
Access RoadSubgrade complete
Gravelling now underway, will
be complete by Aug 8
Tower FndsComplete
Tower ErectionNot started
Acc BldgFnd complete
Conc floor complete
Steelox shell erected
Radar BldgSame status as Acc Bldg
PassagewayComplete except for door and electrical
Building SiteRough graded only
No fencing
Fuel Tanks2000 gal tank in place - no piping
Diesel GeneratorNot delivered

Recommendation re termination of contract:

Advise contractor to cease work at once. If Steelox is to be dismantled then site can be restored to original shape. If not, then fence should be installed.