LUCKNOW
File 62-702-L17-1
Contractor | Looby Construction |
Awarded | May 16, 1962 |
Contract comp date | November 1, 1962 |
Value of contract | $53,000.00 |
Value of work completed July 31, 1962 | $10,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Sub grade complete Sub base complete Surface gravel to be placed at end of job |
Tower Fnds | Poured July 30/62 |
Tower Erection | Not started |
Acc Bldg | Fnds to be poured Aug 3/62 |
Steelox Components | Not delivered to site RCAF placed stop order on delivery Contractor supplied items on site |
Passageway | Fnds not started |
Building Site | Rough grading complete Fencing material on site |
Fuel Tanks | footings for 2000 gal tank poured |
Diesel Generator | Not delivered |
Recommendation re termination of contract:
Contractor should be notified to cease operations at once. Building site can be restored to approximate original conditions. Road would have to remain. If work to proceed, then Steelox components to be shipped at once, otherwise delay claims will be forthcoming.