BATCHAWANA
File 122-7-193-B17-1
Contractor | Foundation Company |
Awarded | December 5, 1961 |
Contract comp date | July 15, 1962 |
Value of contract | $183,000.00 |
Value of work completed July 31, 1962 | $80,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Sub-grade complete except for 2000' Two of four miles surfaced |
Tower Fnds | Excavation blasted now drilling for rock anchors |
Tower Erection | Not started |
Acc Bldg | Sire grubbed |
Radar Bldg | Site grubbed |
Passageway | Site grubbed |
Building Site | Cleared and grubbed Fence not on site Brush control - not started |
Fuel Tanks | Now working on base for 50,000 gal tank Dyke not started Tank erection to start next week 2000 gal tank on site Footings not started |
Diesel Generator | Not on site - expected end of Aug |
Forms and finishing lumber and insulation for buildings on site. Steelox Bldgs - not on site.
Recommendation re termination of contract:
Instructions should be issued to have all work cease at once. I assume little or no site clean-up will be required due to isolated location. Main thing is to prohibit the commencement of 50,000 tank erection. Stop order on diesel delivery should be given. Contractor shoud be told to cancel all materials and sub-contract orders.