TOBERMORY
File 122-7-193-T10-1
| Contractor | Logan Const |
| Awarded | November 3, 1961 |
| Contract comp date | June 30, 1962 |
| Value of contract | $54,000.00 |
| Value of work completed July 31, 1962 | $52,000.00 |
| Current estimated completion date | August 15, 1962 |
| Access Road | Complete |
| Tower Fnds | Complete |
| Tower Erection | Not started |
| Acc Bldg | Complete |
| Radar Bldg | Complete |
| Passageway | Complete |
| Building Site | Complete |
| Fuel Tanks | Complete |
| Diesel Generator | On site, now being hooked up |
Recommendation re termination of contract:
All work should be completed except installation of radar tower.