FORMOSA
File 122-7-193-A15-1
| Contractor | Logan Const |
| Awarded | November 3, 1961 |
| Contract comp date | July 15, 1962 |
| Value of contract | $55,000.00 |
| Value of work completed July 31, 1962 | $45,000.00 |
| Current estimated completion date | August 21, 1962 |
| Access Road | 95% complete |
| Tower Fnds | Complete |
| Tower Erection | Not started |
| Acc Bldg | Complete except for minor electrical and painting |
| Radar Bldg | Same status as Acc Bldg |
| Passageway | Complete |
| Building Site | Rough grading complete fence not erected |
| Fuel Tanks | 2000 gal tank in place connection not complete |
| Diesel Generator | Expected on site any day |
Recommendation re termination of contract:
All work should be completed except installation of diesel generator and radar tower.