122-7-193-S41-1
Aug 8/62
Mr DE Bastedo,
Branch Manager,
Halifax, NS
Gap Filler - Scotch Settlement, NB
The decision in regard to this project is to complete the work. The electrical control panel, if on site, will be shipped to the RCAF for storage and instructions in this respect will be forwarded as soon as possible. The diesel generator will not be shipped as the RCAF have issued a stop order on the shipment of these units.
LD Briden,
Assistant Chief Engineer,
(Field Projects)