ELLIOT LAKE
File 122-7-193-E12-1
| Contractor | Carrington Construction |
| Awarded | December 5, 1961 |
| Contract comp date | July 31, 1962 |
| Value of contract | $96,000.00 |
| Value of work completed July 31, 1962 | $90,000.00 |
| Current estimated completion date | August 21, 1962 |
| Access Road | Complete |
| Tower Fnds | Complete |
| Tower Erection | Not started |
| Acc Bldg | Complete except for floor tile and painting grounding 95% |
| Radar Bldg | Same as for Acc Bldg |
| Passageway | Complete |
| Building Site | Complete |
| Fuel Tanks | 2,000 gal tank completed |
| Diesel Generator | Expected on site Aug 1/62 |
Recommendation re termination of contract:
All work should be completed except installation of diesel generator and Radar Tower.